IBPS PO 2017 Practice Test – Quant Day 6

Hello Aspirants.

Welcome to Online Reasoning Section with explanation in AffairsCloud.com. Here we are creating Best question samples for IBPS PO 2017. We have included Some questions that are repeatedly asked in bank exams !!!

Click Here to View Cumulus Course : IBPS PO 2017 
IBPS PO 2017 : Reasoning Test– 6 PM Every Day
IBPS PO 2017 : Quants Test– 7 PM Every Day

Q(1-5). Study the following Table containing shapes and dimensions of the field.

table-day-6

  1. What is the difference between the cost of fencing for square and Right angled triangle?
    A. Rs. 3052
    B. Rs. 3092
    C. Rs. 2052
    D. Rs. 2592
    E. None
    Answer
  2. Sum of Cost of fencing of all fields together is ?
    A. Rs 144350
    B. Rs 150210
    C. Rs 161280
    D. Rs 174660
    E. None
    Answer
  3. What is the difference between cost of fencing for Rectangle and Parallelogram?
    A. Rs 378
    B. Rs 468
    C. Rs 598
    D. Rs 678
    E. None
    Answer
  4. The perimeter of the Right angled triangle is what percent more than Perimeter of Circle?
    A. 7.23
    B. 6.25
    C. 4.54
    D. 3.33
    E. None
    Answer
  5. Cost of fencing for which of the following fields will be highest?
    A. Right Angle Triangle
    B. Parallelogram
    C. Circle
    D. Square
    E. Rectangle
    Answer

Q(6-10). Each question contains statement followed Quantity I and Quantity II. Find relationship between both the quantities.

  1. Find the Volume
    Quantity I: If the side of cube is 68 metre
    Quantity II: If the diameter of sphere is 84 metre
    A. Quantity I > Quantity II
    B. Quantity I < Quantity II
    C. Quantity I ≥ Quantity II
    D. Quantity I ≤ Quantity II
    E. Quantity I = Quantity II or relationship cannot be established
    Answer
  2. No of Days in which A alone can complete work
    Quantity I: B alone can complete a work in 12 days. C can complete it in 24 days. A and B started work and worked for 3 days. They both left now C finished the remaining work in 9 days.
    Quantity II: A and B complete work in 8 days, B and C can complete work in 12 days, C and A can complete work in 8 days.
    A. Quantity I > Quantity II
    B. Quantity I < Quantity II
    C. Quantity I ≥ Quantity II
    D. Quantity I ≤ Quantity II
    E. Quantity I = Quantity II or relationship cannot be established
    Answer
  3. Find profit percentage
    Quantity I: If CP is 39,900 and MP is 46200 and discount offered on MP is 5%
    Quantity II: If difference between MP and SP is 4840 and discount offered is 10% and CP is 39600
    A. Quantity I > Quantity II
    B. Quantity I < Quantity II
    C. Quantity I ≥ Quantity II
    D. Quantity I ≤ Quantity II
    E. Quantity I = Quantity II or relationship cannot be established
    Answer
  4. Find Interest
    Quantity I: If Sum is Rs 1632 lent at simple interest at 5% rate for 2 years
    Quantity II: If sum is Rs 2000 lent at Compound interest at 4% for 2 years
    A. Quantity I > Quantity II
    B. Quantity I < Quantity II
    C. Quantity I ≥ Quantity II
    D. Quantity I ≤ Quantity II
    E. Quantity I = Quantity II or relationship cannot be established
    Answer
  5. Find X
    Quantity I : X 2 – 84X + 1764 = 0
    Quantity II : X 2 – 86X + 1849 = 0
    A. Quantity I > Quantity II
    B. Quantity I < Quantity II
    C. Quantity I ≥ Quantity II
    D. Quantity I ≤ Quantity II
    E. Quantity I = Quantity II or relationship cannot be established
    Answer

3 Free Tests EveryDay on OliveBoard APP - Download Now