  1. Which of the following model is a combination of Iterative model and Waterfall model?
    A. linear-sequential Model
    B. Spiral Model
    C. V Model
    D. None of the Above
    B. Spiral Model

  2. SRS stands for ________
    A. Software Resolution Specification
    B. Software Requirement Standards
    C. Software Response Service
    D. Software Requirements Specifications
    D. Software Requirements Specifications

  3. Which of the following model is also referred to as a linear-sequential life cycle model?
    A. Waterfall Model
    B. Iterative Model
    C. Spiral Model
    D. V Model
    A. Waterfall Model

  4. SDLC stands for ________
    A. Software Department Load Cycle
    B. Software Department Life Cycle
    C. Software Development Load Cycle
    D. Software Development Life Cycle
    D. Software Development Life Cycle

  5. According to Lehman’s laws of software evolution, the software can be divided into _______ types.
    A. Two
    B. Four
    C. Three
    D. Six
    C. Three

  6. What is the final result of the requirements analysis and specifications phase ?
    A. data flow diagram
    B. SRS Document
    C. Coding the project
    D. User Manual
    B. SRS Document

  7. In software development, What is noise?
    A. Adding requirements in SRS document
    B. Writing irrelevant statement in SRS document
    C. Writing over-specific requirements in SRS document
    D. None of the Above
    B. Writing irrelevant statement in SRS document

  8. The 4GT Model is a package of __________________.
    A. CASE Tools
    B. Software tools
    C. Both (A) and (B)
    D. None of the Above
    B. Software tools

  9. Risk analysis of a project is done in _______
    A. System Analysis phase
    B. Implementation phase
    C. Maintenance phase
    D. Feasibility Study
    D. Feasibility Study

  10. Which of the following is the most important phase of Software Development Life Cycle (SDLC)?
    A. Requirements analysis
    B. Coding
    C. Testing
    D. Designing
    A. Requirements analysis